Question: Below is the information on a small project. All information is in days and the crash time is the amount of time that the project
Below is the information on a small project. All information is in days and the crash time is the amount of time that the project can be shortened along with the associated cost of crashing.
Activity
Time
In Days
Immediate
Predecessors
Crash Time
Days
Crash Cost
P
L
I
N
K
none
P
P
L I
N I
$Day
$Day
$Day
$Day
$Day
Hint: In order to be successful in this activity you must draw out the AON diagram on your own in order to best answer the following questions.
Identify the slack in the project.
Question options:
days at I
days at P
days at L
Any of these are correct.
days at K
days at N
None of these are correct.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
