Question: Below is the information on a small project. All information is in days and the crash time is the amount of time that the project

Below is the information on a small project. All information is in days and the crash time is the amount of time that the project can be shortened along with the associated cost of crashing.
Possible
Activity
Time
In Days
Immediate
Predecessor(s)
Crash Time
(Days)
Crash Cost
P
L
U
N
K
6
3
6
7
9
none
none
P,L
U
U, N
1
2
1
1
2
$200/Day
$100/Day
$150/Day
$300/Day
$500/Day
Hint: In order to be successful in this activity you must draw out the AON diagram on your own in order to best answer the following questions.
What is the most economical way to reduce the project time (crash) by 2 days
Question 15 options:
P-$200, U-$150
Does not matter as long as you crash by 2 days,
L-$100, I-$150
L-$100
None of these are correct.
L-$200
K-$500
I-$300

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!