Question: (35 points) Project Management. Consider the following Precedence Table: Normal Duration Task ID Precedence (Months) Normal Cost ( Millions) Crash Duration (Months) Crash Cost (
(35 points) Project Management. Consider the following Precedence Table:
Normal
Duration Task ID Precedence (Months)
Normal Cost ( Millions)
Crash Duration (Months)
Crash Cost ( Millions)
A-3214 B - 4 3 1 12 C-2214 DC13-- E A,B,C 3 5 2 6
-
(5 points) Draw the (Normal) Project Network Diagram
-
(5 points) What is the minimum project completion time?
-
(5 points) Identify the critical path
-
(5 points) Create a Gantt chart for the project, scheduling non-critical tasks as early
as possible
Crash the project to 4 months
-
(5 points) Draw the Project Network Diagram for the crashed project
-
(5 points) How much does it cost to crash the project 4 months?
-
(5 points) Identify the critical path for the crashed project
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
