Question: (35 points) Project Management. Consider the following Precedence Table: Normal Duration Task ID Precedence (Months) Normal Cost ( Millions) Crash Duration (Months) Crash Cost (

(35 points) Project Management. Consider the following Precedence Table:

Normal

Duration Task ID Precedence (Months)

Normal Cost ( Millions)

Crash Duration (Months)

Crash Cost ( Millions)

A-3214 B - 4 3 1 12 C-2214 DC13-- E A,B,C 3 5 2 6

  1. (5 points) Draw the (Normal) Project Network Diagram

  2. (5 points) What is the minimum project completion time?

  3. (5 points) Identify the critical path

  4. (5 points) Create a Gantt chart for the project, scheduling non-critical tasks as early

    as possible

Crash the project to 4 months

  1. (5 points) Draw the Project Network Diagram for the crashed project

  2. (5 points) How much does it cost to crash the project 4 months?

  3. (5 points) Identify the critical path for the crashed project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!