Question: (35 points) Project Management. Consider the following Precedence Table: Task ID Precedence Normal Duration (Months) Normal Cost ( Millions) Crash Duration (Months) Crash Cost (
- (35 points) Project Management. Consider the following Precedence Table:
|
Task ID |
Precedence | Normal Duration (Months) | Normal Cost ( Millions) | Crash Duration (Months) | Crash Cost ( Millions) |
| A | - | 3 | 2 | 1 | 4 |
| B | - | 4 | 3 | 1 | 12 |
| C | - | 2 | 2 | 1 | 4 |
| D | C | 1 | 3 | - | - |
| E | A,B,C | 3 | 5 | 2 | 6 |
- (5 points) Draw the (Normal) Project Network Diagram
- (5 points) What is the minimum project completion time?
- (5 points) Identify the critical path
- (5 points) Create a Gantt chart for the project, scheduling non-critical tasks as early as possible
Crash the project to 4 months
- (5 points) Draw the Project Network Diagram for the crashed project
- (5 points) How much does it cost to crash the project 4 months?
- (5 points) Identify the critical path for the crashed project