Question: (35 points) Project Management. Consider the following Precedence Table: Task ID Precedence Normal Duration (Months) Normal Cost ( Millions) Crash Duration (Months) Crash Cost (

  1. (35 points) Project Management. Consider the following Precedence Table:

Task ID

Precedence

Normal Duration

(Months)

Normal Cost (

Millions)

Crash Duration

(Months)

Crash Cost (

Millions)

A

-

3

2

1

4

B

-

4

3

1

12

C

-

2

2

1

4

D

C

1

3

-

-

E

A,B,C

3

5

2

6

  1. (5 points) Draw the (Normal) Project Network Diagram
  2. (5 points) What is the minimum project completion time?
  3. (5 points) Identify the critical path
  4. (5 points) Create a Gantt chart for the project, scheduling non-critical tasks as early as possible

Crash the project to 4 months

  1. (5 points) Draw the Project Network Diagram for the crashed project
  2. (5 points) How much does it cost to crash the project 4 months?
  3. (5 points) Identify the critical path for the crashed project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!