Question: Project Management- please answer ASAP 1.1 Determine the critical path of the project (6 marks) 1.2 Calculate the planned duration of the project in weeks

Project Management- please answer ASAP

Project Management- please answer ASAP 1.1 Determine the critical path of the

1.1 Determine the critical path of the project (6 marks)

1.2 Calculate the planned duration of the project in weeks (6 marks)

1.3 Identify any non-critical tasks and the float (free slack) on each (8 marks)

Using the information in the table below, assuming that the project team will work a standard working week ( 5 working days in 1 week) and that all tasks will start as soon as possible

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!