Question: Project Management- please answer ASAP 1.1 Determine the critical path of the project (6 marks) 1.2 Calculate the planned duration of the project in weeks
Project Management- please answer ASAP

1.1 Determine the critical path of the project (6 marks)
1.2 Calculate the planned duration of the project in weeks (6 marks)
1.3 Identify any non-critical tasks and the float (free slack) on each (8 marks)
Using the information in the table below, assuming that the project team will work a standard working week ( 5 working days in 1 week) and that all tasks will start as soon as possible