Question: TASK DESCRIPTION DURATON (WORKING DAYS) PREDECESSOR A Requirement Analysis 5 B Systems Design 15 A C Programming 25 B D Telecoms 15 B E Hardware
| TASK | DESCRIPTION | DURATON (WORKING DAYS) | PREDECESSOR |
| A | Requirement Analysis | 5 | |
| B | Systems Design | 15 | A |
| C | Programming | 25 | B |
| D | Telecoms | 15 | B |
| E | Hardware Installation | 30 | B |
| F | Integration | 10 | C,D |
| G | System Testing | 10 | E,F |
| H | Training / Support | 5 | G |
| I | Handover and Go-Live | 5 | H |
Question 1 (25 MARKS)
1.1 Determine the critical path of the project. (15 Marks)
1.2 Calculate the planned duration of the project in weeks. (4 Marks)
1.3 Identify any non-critical tasks and the float (free slack) on each. (6 Marks)