Question: Project management - Q1:- Draw Activity on Node and activity on arrow diagram for the given data and find Critical Path by finding ES,EF,LS,LF hence

Project management
- Q1:- Draw Activity on Node and activity on arrow diagram for the given data and find Critical Path by finding ES,EF,LS,LF hence Slack for each activity (15) Activity Name Preceding Activity Activity Time (Days) B 7 A 3 C A 2 D B 4 E 6 F D 2 G E.F 3 H G 8 I H 4 J H 3 K IJ 2Step by Step Solution