Question: Project Network Exercise Name: Student ID: Complete the exercise. You will need to 1. Draw in the arrows that indicate the logical flow of the

Project Network Exercise Name: Student ID:

Project Network Exercise Name: Student ID: Complete the exercise. You will need to 1. Draw in the arrows that indicate the logical flow of the network 2. Fill in the duration 2. Conduct a forward pass of the network 4. Conduct a backward pass of the network 5. Clearly Indicate the critical path WAS ID Activity Predecessor Duration Order review A 3 11 A 2 A 8 D A 10 Order parts Prodice parts Design parts Software Dev. Manufacture parts Assemble E A 6 2 F &.C. G 5 H Test FG B ESIDEF SL 15 DURF A H D G Name Student ID