Project Network Exercise Name: Student ID: Complete the exercise. You will need to: 1. Draw in the arrows that indicate the logical flow of the network. 2. Fill in the durations. 3. Conduct a forward pass of the network. 4. Conduct a backward pass of the network. 5. Clearly indicate the critical path. WBS ID Activity Predecessor Duration Order review 2 B Order parts 6 C 4 1 D Produce parts Design parts Software Dev. A E m | 3 F Manufacture parts B,C 6 G Assemble UI DE H Test F G 9