Question: Project Network Exercise Name: Student ID: Complete the exercise. You will need to: 1. Draw in the arrows that indicate the logical flow of the
Project Network Exercise Name: Student ID: Complete the exercise. You will need to: 1. Draw in the arrows that indicate the logical flow of the network. 2. Fill in the durations. 3. Conduct a forward pass of the network. 4. Conduct a backward pass of the network. 5. Clearly indicate the critical path. WBS ID Activity Predecessor Duration A Order review 4 B Order parts A 3 C Produce parts A 2 D Design parts A 5 E Software Dev. A 4 F Manufacture parts B,C 7 G Assemble D,E 2 H Test F,G 4 B ES ID EF SL LS