Question: project network - predecessor activities and activity time in days. The results of their meeting are found in the following table: Part A . Create

project network-predecessor activities and activity time in days. The results of
their meeting are found in the following table:
Part A. Create a network based on the above information. How long will the project
take? What is the critical path?
Part B. Upon further review the team recognizes that they missed three finish-to-start
lags. Procure prototype parts will involve only 2 days of work but it will take 8 days for the
parts to be delivered. Likewise, Order stock components will take 2 days of work and 8
days for delivery and Order custom components 2 days of work and 13 days for delivery.
Reconfigure the CyClon schedule by entering the three finish-to-start lags. What
impact did these lags have on the original schedule? On the amount of work required
to complete the project?
Part C. Management is still not happy with the schedule and wants the project com-
pleted as soon as possible. Unfortunately, they are not willing to approve additional
resources. One team member pointed out that the network contained only finish-to-
start relationships and that it might be possible to reduce project duration by creating
start-to-start lags. After much deliberation the team concluded that the following rela-
tionships could be converted into start-to-start lags:
Procure prototype parts could start 6 days after the start of Design.
Fabricate parts could start 9 days after the start of Design.
Laboratory test could begin 1 day after the start of Assemble prototype.
Field test could start 5 days after the start of Laboratory test.
Adjust design could begin 7 days after the start of Field test.
Order stock and Order custom components could begin 5 days after Adjust design.
Test unit could begin 9 days after the start of Assemble test production unit.
Document results could start 3 days after the start of Test unit.
Reconfigure the CyClon schedule by entering all nine start-to-start lags. What impact
did these lags have on the original schedule (Part A)? How long will the project take?
Is there a change in the critical path? Is there a change in the sensitivity of the network?
Why would management like this solution?
 project network-predecessor activities and activity time in days. The results of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!