Question: Project one Forecasting Based on Hard Rock Caf Case Pg 101-102 /ISBN number 978-0-13-517362-6 At the Hard Rock Cafe, like many organizations, project management is
Project one Forecasting Based on Hard Rock Caf Case Pg 101-102 /ISBN number 978-0-13-517362-6
At the Hard Rock Cafe, like many organizations, project management is a key planning tool. With Hard Rocks constant growth in hotels and cafes, remodeling of existing cafes, scheduling for Hard Rock Live concert and event venues, and planning the annual Rockfest, managers rely on project management techniques and software to maintain schedule and budget performance. Without Microsoft Project, says Hard Rock Vice-President Chris Tomasso, there is no way to keep so many people on the same page. Tomasso is in charge of the Rockfest event, which is attended by well over 100,000 enthusiastic fans. The challenge is pulling it off within a tight 9-month planning horizon. As the event approaches, Tomasso devotes greater energy to its activities. For the first 3 months, Tomasso updates his Microsoft Project charts monthly. Then at the 6-month mark, he updates his progress weekly. At the 9-month mark, he checks and corrects his schedule twice a week.
Early in the project management process, Tomasso identifies 10 major tasks (called level-2 activities in a work breakdown structure, or WBS): talent booking, ticketing, marketing/PR, online promotion, television, show production, travel, sponsorships, operations, and merchandising. Using a WBS, each of these is further divided into a series of subtasks. Table 3.8 identifies 26 of the major activities and subactivities, their immediate predecessors, and time estimates. Tomasso enters all these into the Microsoft Project software. Tomasso alters the Microsoft Project document and the time line as the project progresses. Its okay to change it as long as you keep on track, he states.
Table 3.8 Some of the Major Activities and Subactivities in the Rockfest Plan ACTIVITY DESCRIPTION PREDECESSOR(S) TIME (WEEKS)
A Finalize site and building contracts 7
B Select local promoter A 3
C Hire production manager A 3
D Design promotional Web site B 5
E Set TV deal D 6
F Hire director E 4
G Plan for TV camera placement F 2
H Target headline entertainers B 4
I Target support entertainers H 4
J Travel accommodations for talent I 10
K Set venue capacity C 2
L Ticketmaster contract D, K 3
M On-site ticketing L 8
N Sound and staging C 6
O Passes and stage credentials G, R 7
P Travel accommodations for staff B 20
Q Hire sponsor coordinator B 4
R Finalize sponsors Q 4
S Define/place signage for sponsors R, X 3
T Hire operations manager A 4
U Develop site plan T 6
V Hire security director T 7
W Set police/fire security plan V 4
X Power, plumbing, AC, toilet services U 8
Y Secure merchandise deals B 6
Z Online merchandise sales Y 6
The level-1 activity is the Rockfest concert itself. There are actually 127 activities used by Tomasso; the list is abbreviated for this case study. The day of the rock concert itself is not the end of the project planning. Its nothing but surprises. A band not being able to get to the venue because of traffic jams is a surprise, but an anticipated surprise. We had a helicopter on stand-by ready to fly the band in, says Tomasso. On completion of Rockfest in July, Tomasso and his team have a 3-month reprieve before starting the project planning process again.
Discussion Questions Identify the critical path and its activities for Rockfest. How long does the project take? Which activities have a slack time of 8weeks or more? Identify five major challenges a project manager faces in events such as this one. Why is a work breakdown structure useful in a project such as this? Take the 26 activities and break them into what you think should be level-2, level-3, and level-4 tasks
-
Answer all textbook questions plus these
-
Develop a linear model using The month as a predictor. Simple liner Y=A + BX
-
Develop another simple linear model with advertising as predictor Y=A+BX
-
Develop a linear Model with both Month X1 and advertising X2 or multiple linear systems
-
Use MAD to test all three linear methods. Which of the three is more accurate? Explain.
-
Which of the two variables Month and Advertising is in reality Linear or more Linear? Looking at the graphs.
-
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
