Question: Using the data given, create the project schedule using normal times. Determine the order in which you would want to crash the project one day,

 Using the data given, create the project schedule using normal times.

Using the data given, create the project schedule using normal times. Determine the order in which you would want to crash the project one day, two days, and so on until it is in an all crash mode. Identify how much it would cost for each day you crash the schedule. Activity Predecessor Normal Normal Crash Crash Crash Cost per Time Cost Time Cost Day A 12 200 9 350 B A 8 300 8 300 A 9 250 7 450 D B 6 400 5 600 E B, C 5 150 4 225 F Ic 10 500 9 650 G D. EF 8 400 6 900

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!