Question: Using the data given, create the project schedule using normal times. Determine the order in which you would want to crash the project one day,
Using the data given, create the project schedule using normal times. Determine the order in which you would want to crash the project one day, two days, and so on until it is in an all crash mode. Identify how much it would cost for each day you crash the schedule. Activity Predecessor Normal Normal Crash Crash Crash Cost per Time Cost Time Cost Day A 12 200 9 350 B A 8 300 8 300 A 9 250 7 450 D B 6 400 5 600 E B, C 5 150 4 225 F Ic 10 500 9 650 G D. EF 8 400 6 900