Project phase Duration (month) Predecessors Estimated Budget @$000 Actual cost @ $000 % of completion A 24
Fantastic news! We've Found the answer you've been seeking!
Question:
Project phase | Duration (month) | Predecessors | Estimated Budget @$000 | Actual cost @ $000 | % of completion |
A | 24 | Start | 500 | 550 | 100 |
B | 12 | A | 200 | 225 | 100 |
C | 6 | B | 1250 | 2000 | 100 |
D | 6 | C | 400 | 450 | 100 |
E | 18 | D(SS+4months) | 1800 | 200 | 20 |
F | 24 | D(SS+4months) | 2400 | 300 | 30 |
G | 24 | F(SS+2Months) | 2400 | 600 | 25 |
END | D,E,F.G |
Project phase | Duration (month) | Predecessors | Estimated Budget @$000 | Actual cost @ $000 | % of completion |
A | 24 | Start | 500 | 550 | 100 |
B | 12 | A | 200 | 225 | 100 |
C | 6 | B | 1250 | 2000 | 100 |
D | 6 | C | 400 | 450 | 100 |
E | 18 | D(SS+4months) | 1800 | 200 | 20 |
F | 24 | D(SS+4months) | 2400 | 300 | 30 |
G | 24 | F(SS+2Months) | 2400 | 600 | 25 |
END | D,E,F.G |
a. what is the project lenght , actual cost and total project cost?
b. it is the end of phase D, what are the values for CPI, SPI, EAC and VAC.
Hint: use a day one network diagram and forward pass