Question: The Project Scheduling Problem tab of the 3 Question Parameters workbook displays the Activity-On-Node (AON) diagram for a project network. Activity times (in weeks) are

The Project Scheduling Problem tab of the 3 Question Parameters workbook displays the Activity-On-Node (AON) diagram for a project network. Activity times (in weeks) are shown in the table to the left of the AON diagram. You should:

Enter the "Immediate Predecessors" information into cells B4-B11

Compute and enter the ES, EF, LS, LF, and Slack times for each activity into columns D through H as indicated

Answer the following

How long will the project take? (Enter value)

What is the critical path?

The Project Scheduling Problem tab of the 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!