Question: The Project Scheduling Problem tab of the 3 Question Parameters workbook displays the Activity-On-Node (AON) diagram for a project network. Activity times (in weeks) are
The Project Scheduling Problem tab of the 3 Question Parameters workbook displays the Activity-On-Node (AON) diagram for a project network. Activity times (in weeks) are shown in the table to the left of the AON diagram. You should:
Enter the "Immediate Predecessors" information into cells B4-B11
Compute and enter the ES, EF, LS, LF, and Slack times for each activity into columns D through H as indicated
Answer the following
How long will the project take? (Enter value)
What is the critical path?

Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
