Question: Project Scheduling with Uncertain Time: activity Immediate Time (weeks) Most predecessor Optimistic Probable Pessimistic A 3 5 8 B A 5 7 10 C A

Project Scheduling with Uncertain Time:

activity Immediate Time (weeks) Most
predecessor Optimistic Probable Pessimistic
A 3 5 8
B A 5 7 10
C A 3 6 10
D A 2 6 9
E C, D 1 3 6
F B, C 3 6 10
G E, F 2 3.5 7
H F, G 3 6 10

Be sure to round the expected time to one decimal place.

Be sure to round the variance and standard deviation to 2 decimal places.

Solve the problem and enter your answers to the questions:

1. What are the critical path activities?

2. What is the expected completion time for the project (#of weeks)? (Your answer need to be within 0.1 of the correct answer)

3. What are the variance and standard deviation for the critical path? (Your answers need to be within 0.1 of the correct answer)

4. What is the probability that the project can be completed in more than 30 weeks?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!