Question: Project Task 1 can start immediately and has an estimated duration of 1 day. 2 can start after Task 1 is completed and has an

Project Task

1 can start immediately and has an estimated duration of 1 day.

2 can start after Task 1 is completed and has an estimated duration of 4 days.

3 can start after Task 2 is completed and has an estimated duration of 5 days

4 can start after Task 1 is completed and must follow Task 3 completion date.

Its estimated duration is 8 days.

What is the duration of the critical path for this project?

A.

8 days

B.

12 days

C.

11 days

D.

10 days