Question: Q1. From the table information below i) Draw the network diagram (Points 5) ii) Show ALL the network paths (Points 2) iii) Determine the
Q1. From the table information below i) Draw the network diagram (Points 5) ii) Show ALL the network paths (Points 2) iii) Determine the Critical Path and the total days (Point 3) iv) Determine the float for each activity (Point 5) Activity Duration Dependency Start 0 (days) A 5 (days) Start B 2 (days) Start C 3 (days) A, B D 5 (days) Start E 6 (days) Start F 4 (days) D, E G 2 (days) C, F H 5 (days) G 7 (days) G J 3 (days) H Finish 0 (days) 1,1 i) ii) Project duration (Point 1) Q2. From the table shown iii) Shown the network diagram and calculate the critical path (Points 6) Float of task C (Point 1) iv) Early Start of task E (Point 1) v) Activity Late Finish of Task A (Point 1) Predecessor Duration A 0 5 B 0 6 C A 2 D A, B 5 E B 4 F C, D, E 4