Question: Project X Schedule (a) Use the information in the table above to draw a PERT Chart / Network Diagram, including on each node the task
Project X Schedule
(a) Use the information in the table above to draw a PERT Chart / Network Diagram, including on each node the task name, the task duration, the ES, EF, LS, and LF times. [9 marks]
(b) Use the information in the table above to draw a GANTT chart for the project. [6 marks]
(c) Find the critical path of the project? (Please show Slack Times) [3 marks]
(d) What is the mean duration of this project? [2 marks]
(c) With the aid of a diagram describe Work Break-Down Structure and explain how it can be used to aid in managing a project. [5 marks]
Project X Schedule
(a) Use the information in the table above to draw a PERT Chart / Network Diagram, including on each node the task name, the task duration, the ES, EF, LS, and LF times. [9 marks]
(b) Use the information in the table above to draw a GANTT chart for the project. [6 marks]
(c) Find the critical path of the project? (Please show Slack Times) [3 marks]
(d) What is the mean duration of this project? [2 marks]
(c) With the aid of a diagram describe Work Break-Down Structure and explain how it can be used to aid in managing a project. [5 marks]