Question: Task Predecessor Duration (weeks) E(T) A - 2 B A 1 C - 7 D B 3 E B,C 4 F E 5 G D,F
| Task | Predecessor | Duration (weeks) E(T) |
| A | - | 2 |
| B | A | 1 |
| C | - | 7 |
| D | B | 3 |
| E | B,C | 4 |
| F | E | 5 |
| G | D,F | 1 |
Project X Schedule
a. use the information in the table above to draw a PERT Chart/ Network Diagram, including on each node the task name, the task duration, the ES, EF,LS and LF times. (9 mrks)
b. use the information in the table above to draw a GANTT Chart for the project. (6 mrks)
c. find the critical path of the project? (Including slack time) (3 mrks)
d. what is the mean duration of this project? (2 mrks)
e. with the aid of a diagram describe Work Break-Down Structure and explain how it can be used to aid in managing a project. (5 mrks