Question: Q . 1 0 . For the following task table, draw the network diagram, calculate total duration of the project and find the critical path.
Q For the following task table, draw the network diagram, calculate total duration of the project and find the critical path.
tableTaskSuccessor,Duration daysACBDCE FDF GEHFH I,GI,HI