Question: Q . 2 . for the table below: a ) Draw the node diagram b ) perform the CPM computations ( ES , EF ,

Q.2. for the table below:
a) Draw the node diagram
b) perform the CPM computations (ES, EF, LS, LF, TF, FF) for the schedule below.
\table[[Activity,IPA,Duration,Lag],[A,-,2,],[B,A,6,],[C,A,10,],[D,A,4,4],[E,B,7,],[F,B,5,3],[,C,,],[G,C, D,3,],[H,E, F,5,],[I,G,2,],[,H,,1]]