Question: Q1: The table below defines the activities within a small project. Activity start node end node completion time(week) A 1 2 8 B 2 3

Q1: The table below defines the activities within
Q1: The table below defines the activities within a small project. Activity start node end node completion time(week) A 1 2 8 B 2 3 9 2 4 6 D 4 5 6 E 4 6 7 F 4 7 5 G 5 8 7 H 6 8 8 I 7 8 10 In addition to the above information we have that activities (D), (E) and (F) cannot start until activity (B) has been completed. Also activities (G) and (I) cannot start until activity (E) has been completed