Question: Question 1 The table below defines the activities within a small project. Activity Immediate predecessor - - A B D E F G H Completion

Question 1 The table below defines the activities within a small project. Activity Immediate predecessor - - A B D E F G H Completion Time (weeks) 2 3 4 3 8 3 2 3 B.A DC > F G a. Draw the network diagram. [10] b. Calculate the overall project completion time and identify which activities are critical. [2] c. What is the slack (float) time associated with each of the non-critical activities. [2]