Question: QUESTION 3 (20 Marks) The table below defines the activities within a small project. Activity Duration Predecessor 2 A B 3 4 C A D

QUESTION 3 (20 Marks) The table below defines the

QUESTION 3 (20 Marks) The table below defines the activities within a small project. Activity Duration Predecessor 2 A B 3 4 C A D 3 E 8 BA DC F 3 G 2 E F G H 3 3.1. Draw the Activity on Node network diagram. (10 marks) 3.2. Identify the critical activities. (7 marks) 3.3. Calculate the minimum overall project completion time