Question: Q1.Given the network plan below, develop a loading chart for resources (Electrical Engineers (EE), Mechanical Engineers (ME)) using trial and error approach. Assume that only
Q1.Given the network plan below, develop a loading chart for resources (Electrical Engineers (EE), Mechanical Engineers (ME)) using trial and error approach. Assume that only one of each resource exists at each time period.
a) For the schedule obtained in (a), compute the early, late, and slack times for your project. Define the new critical activities and project duration.