Question: A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate
A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=8.
a.
The critical path is A-C, duration 12.
b.
The critical path cannot be determined without knowing PERT expected activity times.
c.
The critical path is A-B-C, duration 15
d.
The network has no critical path
e.
The critical path is A-B-C, duration 13.5