Question: Q4. The table below shows a project's earned value data. Activity Install fixtures Refinish floors Replace doors Complete tiling Install back door Landscaping Monthly
Q4. The table below shows a project's earned value data. Activity Install fixtures Refinish floors Replace doors Complete tiling Install back door Landscaping Monthly Plan Monthly Act Determine: 7 325 250 14 21 a. Cost variance b. Schedule variance 550 85 28 35 42 49 350 275 1,200 565 875 225 200 325 800 435 1,475 1,440 425 550 550 550 1,100 1,650 550 C. SPI d. The estimated cost to completion % Plan Complete 575 100% 635 100% 625 100% 1,765 80% 1,100 70% 350 350 5,250 1,100 550 25%
Step by Step Solution
3.32 Rating (161 Votes )
There are 3 Steps involved in it
a Cost variance CV can be calculated as the difference between the earned value EV and the actual co... View full answer
Get step-by-step solutions from verified subject matter experts
