Question: A local project being analyzed by PERT has 32 activities, 8 of which are on the critical path. If the estimated time along the critical
A local project being analyzed by PERT has 32 activities, 8 of which are on the critical path. If the estimated time along the critical path is 55 days with a project variance of 25, the probability that the project will be completed in 60 days or less is:
Select one:
Step by Step Solution
3.49 Rating (159 Votes )
There are 3 Steps involved in it
option E is correct Probability0841... View full answer