Question: A local project being analyzed by PERT has 32 activities, 8 of which are on the critical path. If the estimated time along the critical

A local project being analyzed by PERT has 32 activities, 8 of which are on the critical path. If the estimated time along the critical path is 55 days with a project variance of 25, the probability that the project will be completed in 60 days or less is:

Select one:

Step by Step Solution

3.49 Rating (159 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

option E is correct Probability0841... View full answer