Question: A local project being analyzed by PERT has 25 activities, 9 of which are on the critical path. If the estimated time along the critical
A local project being analyzed by PERT has 25 activities, 9 of which are on the critical path. If the estimated time along the critical path is 46 days with a project variance of 36, the probability that the project will be completed in 40 days or less is:
Select one:
Step by Step Solution
3.43 Rating (166 Votes )
There are 3 Steps involved in it
the probability that the project will be completed in 40 ... View full answer