Question: A local project being analyzed by PERT has 25 activities, 9 of which are on the critical path. If the estimated time along the critical

A local project being analyzed by PERT has 25 activities, 9 of which are on the critical path. If the estimated time along the critical path is 46 days with a project variance of 36, the probability that the project will be completed in 40 days or less is:

Select one:

Step by Step Solution

3.43 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

the probability that the project will be completed in 40 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!