Question: Ques 1- What is Critical path method? Ques 2- In your opinion which tool is better CPM or Gantt chart? Why? Ques 3- Below is
Ques 1- What is Critical path method?
Ques 2- In your opinion which tool is better CPM or Gantt chart? Why?
Ques 3- Below is a critical path diagram (with duration in weeks). What does this diagram tell you? What is the total CPM duration for this project?

1J 14 With Durations 15 16 17 2 18 Build Forms 19 4 1 5 5 Strip Forms 20 Excavation Pour Concrete Setting & Curing 21 6 22 Place Rebar 23 24