Question: Question 1 0 ( 1 point ) Consider a scenario that the task content gathering has to be completed before preliminary design and backend setup

Question 10(1 point)
Consider a scenario that the task content gathering has to be completed before
preliminary design and backend setup can start? What is the new total days for the
project?
40
35
25
30
Question 11(1 point)
Consider a scenario that the preliminary design task has been delayed by 5 days.
What is the new total days for the project?
30
40
25
35