Question: Question 1 9 ( 1 point ) A Project manager for a small construction company has a project that was budgeted for $ 1 3

Question 19(1 point)
A Project manager for a small construction company has a project that was budgeted for $130,000 over a six-week period. According to the schedule, the project should have cost $60,000 to date. However, it has cost $90,000 to date. The project is also behind schedule, because the original estimates were not accurate. Who has the primary responsibility to solve this problem?
a Project sponsor
b Project manager
c Manager of the project management office
d Senior management