Question: Question 17 3.31 points (Cho) A project manager for a small construction company has a project that was budguted for 130.000 aver e period. According

Question 17 3.31 points (Cho) A project manager
Question 17 3.31 points (Cho) A project manager for a small construction company has a project that was budguted for 130.000 aver e period. According to the schedule, the project should have cont 560,000 to date. However, it has cost $90,000 to date. The project is also behind schedule, because the original estimates were not accurate. Who has the primary responsibility to solve this problem? a. Project manager b. Senior management c. Project sponsor d. Manager of the project management office