Question: Question 1 : A manual assembly line is being planned to produce a small consumer appliance. The work elements, element times, and precedence constraints are

Question 1:
A manual assembly line is being planned to produce a small consumer appliance. The work elements, element times, and precedence constraints are indicated in the table below. The workers will work for \(420\mathrm{~min}/\mathrm{shift}\) and must produce 381 units/day.(a) Use the largest candidate rule to solve the line balancing problem. (b) For your line balancing solution, compute the balancing efficiency. (c) Solve using ranked positional weighted method and recalculate balancing efficiency.
\begin{tabular}{ccc|ccc}
\hline \begin{tabular}{c}
Work \\
element
\end{tabular} & \(\mathrm{T}_{\mathrm{e}}(\mathrm{min})\) & \begin{tabular}{c}
Immediate \\
predecessors
\end{tabular} & \begin{tabular}{c}
Work \\
element
\end{tabular} & \(\mathrm{T}_{\mathrm{e}}(\min )\) & \begin{tabular}{c}
Immediate \\
predecessors
\end{tabular}\\
\hline 1 & 0.4 & - & 8 & 0.15 & 4\\
2 & 0.5 & 1 & 9 & 0.41 & 5\\
3 & 0.2 & 1 & 10 & 0.2 & 6,7\\
4 & 0.6 & - & 11 & 0.3 & 8\\
5 & 0.25 & 2 & 12 & 0.33 & 9,10\\
6 & 0.3 & 3 & 13 & 0.4 & 11\\
7 & 0.37 & 4 & 14 & 0.62 & 12,13\\
\hline
\end{tabular}
 Question 1: A manual assembly line is being planned to produce

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!