Question: A particular project network has two paths through it: Path A and Path B. Path A has an expected completion time of 26 and a
-
A particular project network has two paths through it: Path A and Path B. Path A has an expected completion time of 26 and a variance in completion time of 5, while Path B has an expected completion time of 35 and a variance in completion time of 25 . What is the probability that this project is going to take more than 45 weeks?
0%
65.54%
34.46%
97.72%
2.28%