Question: Question 1 Activities Normal Time Crash Time Normal Cost Crash Cost Predecessor A . 3 2 1000 1600 B 2. 1 2000 2700 1 1

Question 1 Activities Normal Time Crash Time

Question 1 Activities Normal Time Crash Time Normal Cost Crash Cost Predecessor A . 3 2 1000 1600 B 2. 1 2000 2700 1 1 300 300 D 7 3 1300 1600 A E Lo 6 3 850 1000 B F N 1 4000 5000 G G 4 2 1500 2000 DE a) Find the project completion date for the given project. b) Crash the project to 10 weeks with minimum cost