Question: Question 1 Consider a sequential process with 3 stations. The processing time and number of employees at each station are as follows: Processing time Number


Question 1 Consider a sequential process with 3 stations. The processing time and number of employees at each station are as follows: Processing time Number of Employees Station A: 4 min/unit 1 employee Station B 2 min/unit 2 employees Statione 5 min/unit 1 employee If demand is 10 units per hour, what is the utilization of Station B? h 20.096