Question: Question [ 1 ] : Fill the opposite table. Develop the AON network diagrams for the project. Calculate ES , EF , LS and LF
Question :
Fill the opposite table.
Develop the AON network diagrams for the project.
Calculate ES EF LS and LF using CPM calculations.
Construct a table to show the activity slack time and activity type C: critical or NC: noncritical
Draw Gantt chart of the ES schedule.
Show the activity slack in the Gantt chart.
What is the project completion time?
What are the critical path activities?
What are the slack times of activities and J
How many paths are there in the project network?
Identify all burst activities and merge activities.
What is the probability of completing the project after weeks?
What is the project completion time in which the
tableActivitytableImmediatePredecessorActivityOpariance WeekstableMostLikelyPessimistic,Expected,,ABCDEAFC DGEHEIF GJH I,KHLHMJ K L project completion probability
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock