Question: Question [ 1 ] : Fill the opposite table. Develop the AON network diagrams for the project. Calculate ES , EF , LS and LF

Question [1]:
Fill the opposite table.
Develop the AON network diagrams for the project.
Calculate ES, EF, LS and LF using CPM calculations.
Construct a table to show the activity slack time and activity type (C: critical or NC: non-critical)
Draw Gantt chart of the ES schedule.
Show the activity slack in the Gantt chart.
What is the project completion time?
What are the critical path activities?
What are the slack times of activities G and J?
How many paths are there in the project network?
Identify all burst activities and merge activities.
What is the probability of completing the project after 33 weeks?
What is the project completion time in which the
\table[[Activity,\table[[Immediate],[Predecessor],[Activity]],Opariance (Weeks)],[\table[[Most],[Likely]],Pessimistic,Expected,,],[A,0.5,2,3.5,,],[B,2,5,8,,],[C,3,8,13,,],[D,2,3,4,,],[E,A,3,4,5,,],[F,C, D,3,5,7,,],[G,E,3,4,5,,],[H,E,4,5,12,,],[I,F, G,2,4,12,,],[J,H, I,2,3,4,,],[K,H,2,3,10,,],[L,H,6,6,6,,],[M,J, K, L,2,4,6,,]] project completion probability 90%?
Question [ 1 ] : Fill the opposite table. Develop

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!