Question: Question 1 : From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical
Question : From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?
tableIDDescription,Predecessor,TimeASurvey site,None,BInstall drainage,ACInstall power lines,ADExcavate site,B CEPour foundation,D