\table[[Activity,\table[[Duration],[(hours)]],\table[[Immediate],[Predecessors]]],[A,14,None],[B,10,None],[C,3,None],[D,7,B,C],[E,1,D],[F,1,E],[G,4,A,F]]
(A) The critical path for this project is
(B) The minimum duration of this project is