Question: Question 12 10 pts n a project management problem after employing CPM it was found that A-C-D-F-G- H-K is the critical path; K is the

Question 12 10 pts n a project management problem

Question 12 10 pts n a project management problem after employing CPM it was found that A-C-D-F-G- H-K is the critical path; K is the last node in the path. The times of completing activities F, G. H and K are respectively 14, 10, 28 and 24 days. If ES (early start of Fis 18, what is the project completion time, T