Question: Question 11 10 pts n a project management problem after employing CPM it was found that A-C-D-E-F- G-H is the critical path. The times of

Question 11 10 pts n a project management problem

Question 11 10 pts n a project management problem after employing CPM it was found that A-C-D-E-F- G-H is the critical path. The times of completing activities E, F, G and H are respectively 16, 14, 10 and 21 days. If ES (early start time) of Eis 14, what is the (late finish time) LF of H