Question: QUESTION 14 If Activity A (duration = 3 days) started on Tuesday and Activity B (duration=2 days) can start not earlier than Friday of the

QUESTION 14 If Activity A (duration = 3 days)

QUESTION 14 If Activity A (duration = 3 days) started on Tuesday and Activity B (duration=2 days) can start not earlier than Friday of the same week, then the relation between these activities is: FS1 SS3 FS3 FS2 FF1 None of the above