Question: Question 2 ( 1 0 points ) An activity has a duration of 1 0 days. Its early start is 5 and its late start

Question 2(10 points)
An activity has a duration of 10 days. Its early start is 5 and its late start is 8. This activity has days of total slack.
2
3
4
5