Question: Question 2 : [ 1 5 ] The following table gives the baseline cost and time estimates ( BCE and BTE ) , the cost

Question 2:
[15]
The following table gives the baseline cost and time estimates (BCE and BTE), the cost and time estimates to correct for failure, and the likelihood of failure for each work package in a riverbank dam project.
\table[[\table[[WBS],[Element]],BCE,\table[[BTE],[(wk)]],\table[[Corrective],[(Cost)]],\table[[Corrective],[(Time)]],Likelihood],[M,R 25.000,10,R 5,000,3,0.25],[N,R 18.000,7,R 4,000,2,0.2],[0,R 40.000,6,R 10,000,3,0.3],[P,R 22.000,8,R 6.000,2,0.15],[0,R 17.000,4,R 3.000,1,0.1],[R,R 12.000,5,R 4.000,2,0.2],[5,R 20.000,6,R 5.000,2,0.3]]
2.1. Determine the risk time and risk cost for all the was elements of the project.
(7)
2.2. Determine the critical path and the duration of the project.
(4)
 Question 2: [15] The following table gives the baseline cost and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!