Question: Question 2 1 points Given the following work breakdown structure, what is the critical path for the project? (note, you will have to compute the

Question 2 1 points Given the following work
Question 2 1 points Given the following work breakdown structure, what is the critical path for the project? (note, you will have to compute the value missing in the expected duration column to derive the correct answer.) Task Predecessor Optimistic Most likely Pessimistic Expected A 42 53.17 B Stan 46 56 60 59.00 AB 3 46 c 19 46 61 14.00 c 38 00 os 12.12 O AGD OBCO ACE OBCE