Question: Question 2 2 ( 1 point ) Saved Consider the following: table [ [ Activity , table [ [ Normal ] , [

Question 22(1 point)
Saved
Consider the following:
\table[[Activity,\table[[Normal],[time]],Predecessor],[A,4,---],[B,10,---],[C,4,---],[D,2,A],[E,3,C]]
What is the project's completion time?
 Question 22(1 point) Saved Consider the following: \table[[Activity,\table[[Normal],[time]],Predecessor],[A,4,---],[B,10,---],[C,4,---],[D,2,A],[E,3,C]] What is the