Question: Question 2 . 2 . If the indirect cost for each duration are $ 1 , 5 0 0 for 1 7 weeks, $ 1
Question If the indirect cost for each duration are $ for weeks, $ for weeks, $ for weeks, $ for weeks, $ for weeks, S for weeks, $ for weeks, and $ for weeks, what is the optimum costtime schedule for the project? What is the cost? Activity Normal Time Normal Cost A B C D EE E F G H Crash Cost slope Maximum Crash Time B B H
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
