Question: Question 2 . 2 . If the indirect cost for each duration are $ 1 , 5 0 0 for 1 7 weeks, $ 1

Question 2.2. If the indirect cost for each duration are $1,500 for 17 weeks, $1,450 for 16 weeks, $1,400 for 15 weeks, $1,350 for 14 weeks, $1,300 for 13 weeks, S1,250 for 12 weeks, $1,200 for 11 weeks, and $1,150 for 10 weeks, what is the optimum cost-time schedule for the project? What is the cost? Activity Normal Time Normal Cost A B C D EE E F G H | Crash Cost (slope)010060400302060200 Maximum Crash Time 021102121343423242150200250200250200250300200 B B 2 H 4