Question: Question 2 (2 points) Consider the network presented in the following table. Calculate the slack for activity D. (Enter your response to the nearest whole

Question 2 (2 points) Consider the network

Question 2 (2 points) Consider the network presented in the following table. Calculate the slack for activity D. (Enter your response to the nearest whole number.) Duration Immediate Task (Days) Predecessors A 50 None B 131 A 40 A D 20 E 10 B, D Your Answer: Your